AECOM sought a declaration that the adjudicator had acted outsider her jurisdiction, or alternatively in breach of natural justice, in respect of certain parts of her decision. The dispute arose out of the termination of a sub-contract in the NEC Engineering and Construction Short Subcontract form. Staptina applied to the adjudicator for a declaration that AECOM was not entitled to make any deductions against its termination account for alleged defects. To read the entire article please click here
One word answer? Limiting the adjudicator’s jurisdiction – AECOM Design Build Limited v Staptina Engineering Services Limited [2017] EWHC 723 (TCC)
26/06/2017